POWER
Of all the energy conversion processes in existence,
the U.S. electric power system is the largest and most
complex. Unlike such industries as communications and
transportation, where a demand in excess of supply
produces a "busy signal" or temporary grid lock, the
nature of the electric power system is one of
instantaneously matching supply and demand. Failure to
sustain this balancing act can result in partial or
complete breakdown of the grid system. Even just a
disruption in supply or a merely inadequate voltage can
cause key industries like oil refining and
high-technology manufacturing to suffer expensive
shutdowns and lengthy production line recovery times.
With deregulation introducing market principles into
the power industry, concern over the reliability of the
electricity supply has magnified. This is because the
emphasis seems to be shifting from reliability as the
mainstay of the nation's essential power base to
reliability as a commodity in the power market.
At the root of all the changes is the industry's
movement from simple "wheeling" (trading power) between
utilities to wholesale and retail competition among
utilities and distributors, a move that was initiated in
part by the 1992 Energy Policy Act and Order 888, issued
by the Federal Energy Regulatory Commission (FERC),
Washington, D.C., in 1996. Now, nonutility generators
not only have the right to sell into the market, but
also are afforded open and equal access to the
transmission grid—all to foster competition, increase
efficiency, and lower energy costs. Consequently, issues
of reliability and security have come under pressure
from financial interests, and utilities' previous
"obligation to serve" has been supplanted by
entrepreneurial vigor [see ""].
Since the issuance of the commission's Order 888, the
paramount concerns within the industry have been that:
-
Market economics would define the optimal
cost/benefit tradeoff that determines how
system reliability is maintained and provided.
-
Voluntary cooperation between utilities
and integrated planning would disappear.
-
Voluntary compliance with reliability
issues would be lacking to the detriment of
the global network.
-
Open access would lead to multiple
transactions, system overloads, and
operational difficulties.
The current and near
future
In the face of these concerns, the U.S. electric
power industry has performed a mammoth task in moving
forward in its restructuring efforts while keeping the
lights on. It is true that a high degree of chaos still
exists, but it must be remembered that, despite the high
level of cooperation that has existed in the past, the
U.S. industry is greatly fractured. Today's electric
utilities exist in many forms—investor-owned,
state-owned, federally owned, and municipals. What's
more, each state has its own Public Utility Commission,
and interconnections cross utility and state boundaries.
To review progress in North America, it is often
helpful to look overseas to see how the global move to
privatization and restructuring is functioning there.
But the comparisons for electric power are often futile.
Much progress has been made, for example, in nations
whose countrywide systems consist of a single entity. A
case in point is the United Kingdom, where privatizing
the system was a comparatively simple process. The
Central Electricity Generating Board both generated and
transmitted power to 12 area distribution companies
within an area that is about the size of New York State.
In the midst of chaos in North America, however,
several key initiatives in the energy market are
focusing on reliability issues, notably the work of the
North American Electric Reliability Council (NERC),
based in Princeton, N.J., and its regional reliability
councils.
NERC at work
One such initiative focuses on simplifying and
standardizing information on complex energy transactions
taking place in the interconnected networks of North
America. To improve the flow of such information and
describe transmission limits in a consistent and
commercially viable manner, NERC has developed such
tools as the transaction information system and the
interchange distribution calculator.
The transaction information system tags all
interchange transactions with information on sources,
intermediary entities, and destinations. These data are
in turn fed into any one of the 22 designated security
coordinators that are spread throughout the NERC regions
and are tasked with identifying conditions that threaten
system security. The coordinators use the interchange
distribution calculators to determine which transactions
are affecting the loading of critical transmission
facilities.
Building on today's area-to-area limit expressions,
NERC panels also developed a so-called flowgate, which
is intended to measure and monitor total network and
transaction impacts on a relatively small number of
whole network interface points.
Another development that has been introduced through
NERC is the transmission reservation and scheduling
process. This procedure facilitates the reservation and
scheduling of transmission service by transmission
customers reliably, in accordance with the actual flow
that would result on the system from proposed
interchange transactions.
An early parallel information source, intended to
promote competition, is the so-called available
transmission capability, or ATC. Designed to communicate
to generation buyers and sellers whether sufficient
transmission capability is available between sources and
sinks, ATC is calculated and published on an
Internet-based bulletin board system called Oasis (for
Open Access Same-time Information System) [see
"Midnight at Oasis:
tapping into scarce transmission
capacity"]. If transmission capacity is
available, a buyer and seller can reserve a firm or
non-firm transaction on the interface, reducing the ATC
available for the next potential user of that transmission.
Of great importance in this restructuring effort is
NERC's desire to transform itself from a watchdog entity
into a self-regulating reliability organization,
authorized to mandate compliance with planning and
operating standards. (Established by the utility
industry following the Northeastern blackout in 1965,
NERC's objectives were to develop planning and operating
standards, criteria, and guidelines that would ensure
the overall reliability of the system.)
So far this plan has worked on a voluntary basis with
rather successfully. But NERC must now extend its
charter to recognize new industry participants, such as
merchant plants, energy marketers, and power brokers.
More importantly, NERC must address the concern of
traditional members that "independence" and market
economics will not lead to acceptable system
reliability.
To that end, NERC has issued fresh planning and
operating standards, very much in line with its own
existing standards and those of its regions, fleshing
out information and performance reporting requirements.
The group has also moved to define compliance
requirements for all entities using the bulk power
system, including erstwhile non-NERC participants, and
has proposed penalties for noncompliance. A pilot
program begun this year is testing the compliance
processes and evaluating the efficacy of the information
reporting and associated sanctions.
Mandating compliance
What NERC will need, of course, is legislated
authority to mandate compliance. Of relevance are the
findings of the Secretary of Energy's Advisory Board
Task Force on Electric System Reliability. The task
force has emphasized the need for congressional
clarification of exactly what authority FERC has over a
self-regulating industry reliability organization, and
of possible expansion of its jurisdiction for
reliability.
In parallel with that finding is the DeLay-Markey
Bill, HR-4432, which would amend the Federal Power Act
to grant FERC the jurisdiction it needs over electric
reliability organizations, operators, and users of the
bulk-power system so as to enforce compliance with U.S.
standards developed by NERC. That bill, introduced last
year, missed congressional deadlines and is destined to
be re-introduced.
FERC's order for open access and the industry's
concern for maintaining reliability amidst all the chaos
is answered in great part by the establishment of
regional regulating bodies called independent system
operators (ISOs). The requirement for independence stems
from the need for nondiscrimination and clear separation
of system operation from participation in the market. As
the name suggests, the ISO "operates" the system and,
depending on its terms of reference, has daily
responsibility for such matters as processing requests
for and scheduling transmission service, managing
congestion, ensuring provision of ancillary services,
coordinating maintenance, and generally maintaining
security. Whether or not an ISO does planning will
depend on how its responsibilities are defined and how
its efforts are coordinated with transmission owners.
The structure and function of ISOs appear well
established. California set the trend by starting ISO
operation in 1998, coordinating ISO efforts with a power
exchange and defining procedures for bidding line load
relief and congestion management. Before it formally
became an operating entity, however, the California
ISO's trustee had the foresight to investigate and
identify "must-run" units to ensure reliability of the
network. This study highlighted the crucial nature of
generation locations in relieving transmission
constraints and providing voltage support, emphasizing
the fact that generation is more than just a source of
energy.
What the ISO's future role may be in providing the
solution to coordinating the need for both facilitating
the market place and maintaining system security is
already evident. In looking at the ISOs now functioning
throughout the continent—in New England, the
Pennsylvania-New Jersey- Maryland area, New York, and
Texas—it is interesting to note that the models and the
mandates are not the same. New York, in particular,
provides for a separate entity, independent of its ISO,
to define reliability objectives and measures. Many of
these structures can be expected to continue through a
transitional period as the industry sorts out its needs.
Distribution issues
At the distribution level, utilities have always
tried to maintain and improve reliability, but in a
relatively haphazard way. With today's sophisticated
analytical tools, reliability levels can be quantified
and cost/benefit tradeoffs can be plotted. Some states
have even mandated reliability targets and use
performance-based rates to enforce adherence to the
target levels. The difficulty with this approach is
identifying the cause of unreliability. Faults on the
transmission system can affect the distribution system.
A further concern is the disparity between the types
of distribution customer. A reliable supply is more
costly to provide in a rural than in an urban area or
city. Besides it is not necessarily correct to provide
every customer with the same reliability.
Still, in high-density areas, it is difficult, if not
currently impossible, to have customers each select
their own level of reliability on a tariff basis. Under
a competitive structure it will be important to ensure
that disincentives are not placed on distribution
companies that demonstrate poor reliability in rural
areas. The Texas Public Utilities Commission, for
instance, took steps to reduce the risk of pockets of
unreliability by mandating that utilities not let two
feeders from the same substation fall on the 10
worst-performing feeders list two years in a row.
The nightmare of inadequacies
With all the activity taking place, it could be
imagined that reliability is in good hands. Most of this
movement, however, is reactive rather than proactive.
While this statement may appear to be contentious under
other circumstances, it is perfectly appropriate when
applied to the disorder prevailing today as the power
industry makes the transition to a market environment.
The philosophy—that competition will introduce
low-cost energy and the marketplace will stimulate
adequate generation capacity—gains credence from the
number of merchant plants being readied for the
Northeast. (At last count, about 25 000 MW of new
generation capacity has been proposed in New England to
serve a peak load of 20 000 MW already being served by
existing generation and imports.) There is some comfort
to be taken from this phenomenon, at least with respect
to the reliability of generation in that area.
From the point of view of security of operations,
however, the industry could be headed toward a nightmare
if transmission planning is inadequate. The concern
stems from the fact that in a market environment, there
is less control, and larger uncertainty, in the
near-term dispatch and longer-term source and
availability of generation.
The characteristics of modern, gas-powered
generation, favored by entrepreneurs, include high
efficiency and fast installation, among others. The
ability of transmission providers to supply additional
capacity continues to be hampered by siting, licensing,
and environmental issues. Where before generation
planning lead subsequently to transmission planning in
an achievable time frame, now generation expansion is
happening much more rapidly and, more importantly,
without the benefit of global planning. The transmission
planner is thus faced with a future full of
uncertainties and unknowns.
Utilities worldwide are confronting this problem,
some more successfully than others. Efforts have been
made in Mexico, Central America, and Southeast Asia to
identify planning methodologies to deal with it.
EletrobrĂ¡s in Brazil, for instance, is embarking on the
development of planning methodologies for the short,
medium, and long term in full knowledge that the
restructuring of the power industry will introduce great
uncertainty in generator rating and location—to the
planners' chagrin. But utilities in the United States,
under the pressure of a rapidly changing environment,
have not yet collectively faced this prospect.
It is clear that many of the current initiatives for
ensuring reliability focus on facilitating transactions
on the basis of "available" transmission. Two issues are
worth consideration. First, an increasing number of
transactions does not introduce transmission congestion
(the congestion myth). Second, a system operator has at
its disposal only those lines and equipment installed as
a result of planning.
As an initial examination of the congestion myth,
suppose that on the first day after FERC issued its
Order 888, every generating unit in the system were
divested (if not already independent) such that each
were subject to a bilateral transaction (total trades
equal to total demand). At that time, to within a few
percent, the power-flow conditions would be identical to
those prior to Order 888 despite the existence of
thousands of transactions.
Simply stated, neither the generating units nor the
load centers would have been relocated. Power flow is a
spatial phenomenon. It is the combined location of
demand and generation that determines the loading on
each transmission line. With the influx of new
generation units now plugging into the existing network
at random locations, stress is created [Fig. 1].
The top of Fig.
1 shows two load centers being served by two
plants so that 500 MW must flow from area A to area B.
The assumed transmission limit is 500 MW. Now assume
that a new industrial demand of 200 MW locates at B and
sets up a contract with a new 400-MW merchant plant.
That plant sells 200 MW to the industrial factory and
the balance to the rest of the world. If the new plant
sites at A, then the transmission flow would increase to
700 MW.
Apparently, the new transaction has resulted in
congestion. If, however, the new plant sites at B, the
new load will be served and the transmission path become
unloaded. The proverbial rocket scientist is out of work
here. The transaction does not cause congestion. Rather,
it frees up transmission capacity. Clearly plant siting
is the important factor. When ATC calculations are
performed as a function of transaction impact, they are
merely identifying the impact of plant location.
'Planning is everything'
In examining the system operators' problem, it is
useful to remember Winston Churchill's observation that
"A plan is nothing. Planning is everything." Given that
a high-cost energy region can attract merchant plants
like bees to honey, transmission providers are attacking
the need to accommodate new plant offerings the way they
best know how: through legitimate application of
regional and NERC deterministic planning criteria. The
task can be onerous, especially when financial forces
conflict with the need for comprehensive evaluations of
the impact of each additional plant on the transmission
system's capability. The idea is to handle injection at
the plants' preferred location. As Fig. 1 shows, plant
location plays the key role, and multiple plant
additions require an evaluation of their several and
joint impacts.
What Fig. 2
illustrates is that supply to the two load centers
cannot be achieved if generator C is not dispatched. The
transmission path limitations are again 500 MW. Putting
this another way, generators A and B cannot be
dispatched together at their full capacities of 400 MW
and 300 MW, respectively, without overloading the
transmission. To avoid line overloading, generator C
could be dispatched instead of generator B. Another of
many possible solutions is to assume that generator C is
always dispatched with at least 200 MW against any
combination of A and B totaling no more than 500 MW.
This simple example is what operators' nightmares are
made of.
In the real world of dynamically complex networks
with dozens of interdependent units, planners are
currently attempting to accommodate all new applicants
through an ongoing design of future, robust transmission
networks that have the capacity to handle many dispatch
combinations.
Under financial and regulatory pressures, however,
planners could be forced to shortcut their analyses in
order to find any workable dispatch for a plant or group
of plants. The number of untenable dispatch conditions
could grow rapidly. At the best of times, with the
elements put at their disposal by the planners,
operators struggle to maintain security on a day-to-day
basis. If planning requirements are to fall short of
traditional exigencies, the operators' task will become
even more arduous.
One example of the impact of open access on
operations security was demonstrated on 25 June 1998,
when an event occurred in which a large area of the U.S.
Mid-Continent Area Power Pool (MAPP) region became
separated from the rest of the eastern interconnection.
Although not cited as a direct cause, the report on the
disturbance discussed the difficulty system operators
face in the deregulated environment when an outage makes
the system unable to withstand a second severe
contingency. While this is a problem with a solution, it
portends a more complex life for operators who must deal
with an expectation of reduced security.
Exacerbating the situation, the well-meaning hand of
the "regulator" is becoming somewhat intrusive. In 1992,
a review of security standards was initiated by the
National Grid Co. PLC, in Britain, in response to the
regulators' concern over the high cost of security
constraints. Currently, during maintenance and other
outages, the National Grid's security standards require
the possibility of constraining off specific generation
to ensure system security.
Among the regulator's suggestions was to relax the
National Grid's fault criteria to a less strenuous
level. While in the public interest in terms of the
overall cost of energy, this advice is tantamount to
trading off security in the interest of lower prices. In
an excellent and comprehensive review that examined
various responses to the regulator's concerns and
suggestions, National Grid concluded that a relaxation
of the existing standards would markedly decrease
reliability.
FERC, too, has showed its hand following a complaint
from Champion International Corp., Stamford, Conn., and
Bucksport Energy Corp., Bucksport, Me. The complainants
charged that "...their access to the New England Power
Pool (NEPOOL) Pool Transmission Facilities has been made
uncertain and prohibitively costly as a result of
delayed placement of Bucksport in the NEPOOL System
Impact Study (SIS) transmission request queue and that,
under ... existing SIS requirements, complainants will
be required to pay for system upgrade costs that may be
unnecessary."
FERC found that "NEPOOL's existing SIS procedures are
based on unrealistic assumptions, produce unreliable
cost estimates and are not otherwise
justified....Bucksport and other project applicants who
may be similarly situated should be allowed to connect
to the NEPOOL [system] without regard to the expansion
cost estimates resulting from NEPOOL's existing SIS
criteria....and Bucksport's request to use economic
redispatch [should be granted] in lieu of paying for
[system] upgrades until such time as NEPOOL implements
revised SIS procedures."
Of interest is the commission's ruling that the
connection is allowed before the cost of necessary
reinforcements is evaluated, which translates to "before
necessary reinforcements are understood and planned."
The ruling demonstrates the manner in which financial
forces, not reliability, will drive, and are driving,
the structure of transmission networks.
In California, the ISO has resorted to signing
short-term (one-year) "reliability must-run" contracts
to ensure availability of generation during extreme
conditions—in the hopes that a transmission solution
will be available at some future date. Who will fund and
construct transmission reinforcements—and how—are key
questions. Perhaps this is another case where the market
concept has leapt forward into reality while a
complementary structure for reliability was yet to be
defined.
So far generation additions are running ahead of
planning transmission enhancements so that the
operator's role in life will no doubt be one of coping
with constraint management rather than contending with
accommodation of bids. Economic redispatch and
congestion management will not further the cause of
either open access or reduced energy cost to consumers
and, with a mountain of untenable dispatches and
constraint procedures to handle, the operator's life
will be a crapshoot.
So, what to do?
Several measures are in order:
First,
educate. Both FERC and prospective plant
owners need to recognize that integration of a power
plant into a large-scale electric power system requires
a comprehensive and sophisticated analysis of
transmission requirements. It is not akin to plugging in
the latest videocassette recorder. What's more, without
a robust transmission system, there can be neither "open
access" nor cost savings to consumers. Unless time is
allowed to plan transmission reinforcements and build
them (if they can be built), both generation and
transmission reliability will suffer. Transmission
system security will be depleted by complexity and lack
of capacity. And generation reserves, no matter how
large, will be inaccessible.
For the future, operator training and enhanced
on-line security assessment tools are
essential—primarily because transmission capacity is
most likely to lose ground. Two big footholds are that
new gas-powered generation can be tendered and installed
quite quickly, and crucial work is being done on
operator training and development of enhanced software
tools for operations.
Next, improve
planning. The NEPOOL situation highlights the
complexities of handling many requests for access in a
short time frame. More importantly, it emphasizes the
need for development of planning methodologies that can
handle future uncertainties. This is an area in which
NERC, despite its important endeavors, has fallen short.
Its move to a self-regulating reliability organization,
coupled with the development of (not entirely) new
planning standards, has not dealt with the problem of
how to plan a network when information on future
resources is unavailable or uncertain.
Essentially, NERC has regurgitated rather than
reformulated. While conventional deterministic planning
criteria and methods have been advocated, enhanced now
with more comprehensive data and information reporting
for mandated compliance, they fail to meet future needs.
There is also a need to embrace already available
planning methodologies capable of handling new
complexities. Methods should accommodate uncertainty and
risk, statistical analysis should play a greater role,
and cost/benefit and customer impact need to be factored
in. Some utilities are already embracing these ideas.
Furthermore, as market hedges and insurance against
failure to deliver or transmit gain prominence,
statistical analysis of the system will take on a
greater significance.
Among other gaps to be filled, generator-siting
techniques should be developed to include the effects of
available resources, existing energy costs, available
transmission, and environmental acceptability. New plant
owners should also be encouraged (presumably
financially) to build where their location will enhance
the overall system and maximize their own availability.
As an adjunct to that goal, the potential impact of
distributed generation should be recognized. There are
pluses and minuses. Locating generation close to or at
loads will reduce dependence on transmission. But
injecting power into a distribution system, has always
been an exercise fraught with difficulties of
protection, stability, and equipment rating. It is not
too early to begin formulating new ideas on the
structure and topology of distribution systems to
exploit these new technologies. The question is far
bigger than mere connection facilities design.
Keep oversight
nonintrusive. FERC should continue to take
care of the public good by firm oversight of procedures
and market making, but it should also avoid too
intrusive a role in the complexities of system design
and operation. Similarly, congressional action on behalf
of mandating reliability should resist going beyond
oversight and granting of authority to mandate
compliance with reliability standards. Unlike a
telephone system, the market is not in the network but
in the providers of energy.
Above all, address
transmission inadequacies. Open access
was predicated on the false belief that the transmission
system was a transportation network. In fact, it is a
system of conductive paths, largely uncontrolled, which
at any time may collapse just from the manner in which
it is used. Without an available, robust transmission
network, operators wage an endless, losing battle.
Special protection schemes, application of Facts
(flexible ac transmission system) devices, and
congestion management tools cannot replace capacity. In
the desire to find cheaper, more efficient ways to
supply power for the lights, the industry may have
risked its ability to keep the lights on.
Spectrum editor:
William Sweet
For a discussion on the ambitions of the North
American Electric Reliability Council (NERC) to
transform itself into a self-regulating reliability
organization with authority to mandate compliance, see
"Reliable Power: Renewing the North American Electric
Reliability Oversight System," prepared by NERC's
Electric Reliability Panel, Princeton, N.J., 22 December
'97.
For a report on the Department of Energy's
deliberations about the Federal Energy Regulatory
Commission's authority over NERC and over power
reliability in general, see "DOE Task Force Emphasizes
Necessity of Increased Efforts to Ensure System
Reliability," printed in Washington
Letter, Edison Electric Institute, 16 October 1998.
A detailed description of the outage that occurred
in the mid-continental region (the agrarian Midwest)
appears in "Transmission System Open Access Versus
System Reliability: A Case History-The MAPP Disturbance
of June 25, 1998," presented by Karl N. Mortensen at the
winter IEEE Power Engineering Society meeting in New
York City, January 1999.
The costs of transmission security constraints are
discussed in a British context in "A Review of
Transmission Security Standards," The National Grid Co.
PLC [London], August 1994. For background on the
Bucksport case, see USA FERC Docket No. EL98-69-000.