Editor’s Note: The
following is Tata Power Company’s description of the
islanding system it employs to avoid catastrophic
blackouts in Mumbai when the regional grid the
utility is connected to goes down. The text was sent
to Senior Editor Harry Goldstein as part of the
research for his article, “How to
Blackout-Proof a City.” It has not been altered
from the original.
ISLANDING OF POWER SYSTEMS
1.0 INTRODUCTION
The electrical load on a system at any given point of
time in conjunction with the on line generating capacity
determines the system frequency. If the load is well
within the on line generating capacity of the system,
then the frequency can be maintained at 50 Hz. Similarly
if the actual generation is less than the load, then the
frequency drops and settles below 50 Hz. The type of
loads and their distribution in the power system also
determine the operational behaviour of the power system.
In any power system, the transmission network is
designed to be adequate for normal load flows and also
for certain reasonable contingencies. However, when
there is a major disturbance with considerable loss of
network/generating capacity, the remaining network may
not be in a position to cater to the load and
generation. This may result in overloading and cascade
tripping of the remaining network following the disturbance.
2.0 SYSTEM OPERATION
UNDER SUDDEN LOSS OF SUBSTANTIAL GENERATING CAPACITY
In any power system under normal circumstances a load
generation balance is achieved which in turn governs the
system frequency at any instant of time. Any small
difference between generation and load is adjusted by
change in generation by the operators or by the
frequency settling to a new value. However, when there
is a sudden loss of large percentage of generation of
the order of 20% percent and above, if no immediate
corrective action is taken. It is likely that system
might become unstable and in the process cause damage to
plant and equipment apart from loss of power supply to
consumers. Also, when there is a total system collapse,
system restoration takes considerable time, due to the
complexity involved in bringing back a major power
system, back into service. However, even if a part of
the total system remains in service, supplying a portion
of the total system, it is relatively quicker to restore
the remaining system back into service. In view of the
above the corrective action under such situation has to
be instantaneous and drastic to arrest the system from collapsing.
: 2 :
In order to protect the power system integrity during
system disturbances certain system protection measures
have to be adopted.
Some of the important system protection measures that
are adopted are:
a) Automatic under frequency load shedding scheme/line
overload trimming scheme/under voltage load shedding scheme
b) System islanding scheme
2.1 Load Shedding Scheme
The principle of automatic under frequency load
shedding scheme is that by relieving definite quantum of
load at different frequencies attempt is made to arrest
the downward drift of the system frequency from reaching
the point where the thermal machines are set to trip by
their protection. However, when the system is subjected
to a disturbance of severity beyond the protection
capacity of the scheme, the system frequency may reach
the thermal unit trip setting. This would result in the
tripping of all the thermal units in the system where
such trip protection is provided. In most of the Indian
power systems, which are predominantly thermal, such a
situation would result in total system collapse.
2.2 System Islanding
In order to provide a further layer of system
protection, following major system disturbance a scheme
called islanding scheme has been developed. This
protection is really a system protection of last resort.
This scheme pre supposes that the integrity of the
system cannot be maintained in spite of the automatic
load shedding, for every possible emergency. Instead of
allowing the system to disintegrate by the tripping of
generators and transmission lines as the disturbance
develops, the islanding scheme itself sectionalises the
whole system into sustainable small systems each
consisting of a group of generating stations and a group
of load that can be supplied by these generating
stations. In effect each group becomes a sustainable
island and hence the name islanding scheme.
: 3 :
3.0 TPC SYSTEM
ISLANDING SCHEME
3.1 Tata Power had developed and commissioned a system
islanding scheme co-ordinated with an automatic under
frequency load shedding scheme a number of years back.
The scheme had saved the Tata Power system from
collapsing on a number of occasions.
3.2 The Tata Power Islanding scheme isolates Tata
Power system from MSEB and BSES at all the
interconnecting points when the system frequency reaches
set …. and there is a net reversal of power from Tata
Power to MSEB and BSES. Before the islanding scheme is
initiated, load shedding by under frequency and rate of
change of frequency relays are carried out at higher
frequencies to stabilise the system frequency from
dropping. Only if frequency continues to drop further,
the islanding scheme is initiated. At the end of
successful islanding, Tata Power system operates as an
islanded system with reduced load but with its own
generation with system stabilised.
3.3 System Restoration
Normal thermal units take about 6 to 8 hours to be
brought back on line, once these have tripped due to any reason.
Tata Power has 1 x 180 MW combined cycle power plant
(which uses gas as fuel) and which can supply 120 MW in
30 minutes and can supply full load within three 3 hours.
In addition, hydro station of Tata Power at Khopoli,
Bhivpuri and Bhira can be brought to full load within a
short span of 30 minutes and power supply to essential
services viz. Railways, essential consumers of BEST like
Hospitals, etc. can be resumed at the earliest. The
above system provides power supply of the highest reliability.
To see all of
Spectrum's special report on The
Megacity, including online extras and audio and
video exclusives, go to http://spectrum.ieee.org/moremegacity.